Friday, 17 June 2011

Tile Work

Had a quick meeting with tiler this morning.  They will be working till next week to get the tiles in the wet areas sorted.  Tiles was delivered on Wednesday apparently and its looks great.  Can't wait for it to be layed.








Wednesday, 15 June 2011

Exterior Work Finish

Hey everyone

I have been quite busy at work recent weeks so haven't been updating the blog very much not to mention getting stuck in SYD when Tiger decided to cancel our flights.  Anyway, there has been quite a lot of action at the site.  The exterior works have pretty much all been finished.  Scaffolding has been removed yesterday and all of the eves and matrix cladding has gone on and painted.  Interior cabinets should have been finished last Saturday according to SS.  Tiles will be delivered today for tilers to start off tiling wet area this week.  SS said that tilers will need around 1 week to finish tiles if all goes according to plan.

Despite the great progress, we did run into some problems.  The fix windows in ensuite 2 was too long and actually extended below the bench cupboard therefore SS will need to order new windows and get brickies in to re-work around that windows.  It will be a non-cost variation.

Still, Metricon has made great progress in the last few weeks.  Fingers cross that the great work carries through to the end!

Monday, 30 May 2011

Gyprock, garage roof and brick done!!!

Gyprock, garage roof and brick has all been completed since the last update.  House  does look bigger with the gyprock like everyone said.  SS said that this week, the carpenter will start work on external matrix cladding and other fittings.  Stair is due in on Wed/Thur.  Carpenter will hopefully be able to start on internal work next week if I remember correctly.
We are officially at our halfway mark this week.  Everything looks like it is progressing well so handover should be still around Aug/Sept.  Fingers cross!







Tuesday, 17 May 2011

Insulation in and 1st floor wrap

Went to site this morning and found insulation went in yesterday and 1st floor wrapped.  We went for R1.5 acoustic insulation for our house as the insulation companies that I spoken to recons that there really isn't that much gain from R1.5 to R2.5 so it was more cost effective with R1.5.  But after seeing the R1.5 insulation in person, it seem quite thin...  Maybe should have gone with R2.5.





Saturday, 14 May 2011

Progress so far this month

Hey guys

Just to update the recent work done.  So far the scaffolding, gyprock, 1st floor brick has been deliver.  The roof beam on the garage has been also installed.  Ground floor brick has been finished.  We have also ask the plumber to connect a town water tap for the laundry as we might not want to use rain water to wash the cloth for our infant.  We have found out we have different option of setting up the hot water control switch located at the kitchen.  Apparently there are 2 ways of setting up the hot water system.  Option 1, we can have the switch controlling the whole hot water temperature of the whole house where allow adjustment to the maximum of 50oC.  Option 2, we have the switch controlling the kitchen tap only where we can adjust the kitchen tap to a maximum of 60oC and the rest of the house will run at the pre-set temperature of 50oC.  Option 2 involves getting a different hot water system that can go up to 60oC instead of standard 50oC hot water system. We went with option 2 coz we thought might come in more handy with hotter water at the kitchen sink plus we probably wont see ourselves adjusting lower than 50oC since my wife loves hot showers. 









Yesterday I drove by to find the scaffolding already installed for next week.  Next week will be a busy week.  Insulation need to go in the exterior walls and the internal bedroom walls.  Gyprock is going be installed on Tuesday.  In the same time the exterior 1st floor wall will be wrap and brick work hopefully will be finish for the whole house too.  Our SS is starting to get a bit panicking since everything has taken bit longer than expected due to the size of our house.  But he was quite happy telling that he has figure out a whole building plan for our house from next week onward which should see our house built in time.  Figures cross that we get a fine weather next week on.

Tuesday, 3 May 2011

Brick Started

Brick work finally started last Thursday due to the wet weather.  Our SS is back from his holidays too.  He told me that brick will take probably around week and half for the whole house without rain. 

The brick layer were back in full force today on their second day on the bricks.  We will be rendering after settlement so please note that this is not going to be the finish colour of our house.